|
Dr Shaw Mead
from ASR Limited in New Zealand
was in St Francis Bay from 15 to
17 May, 2006 to report back on
the findings from the ASR
Draft Report on the SFB
Beach Project to the SFB
Beach Trust.
In addition a
Public Meeting was also held on
17 May in order to brief SFB
residents on progress on the
project this far. The meeting
was well attended and over
seventy residents were there to
listen to Shaw Mead review the
current position and findings.
Key Issues
The
presentation focussed on the key
issues flowing from the data
collection phase which is well
advanced, as well as the draft
recommendations flowing from the
research. The main focus points
were as follows:
-
Beach Erosion: The
beach will continue to erode
but has reached a stage
where erosion is slower than
in the past, as the natural
rock structures in the sea
are inhibiting rapid
erosion. However, the
offshore section of the
beach has deepened
considerably since the
previous bathymetric survey
in 1953.
-
Previous Studies: The
groyne option recommended
previously by the
consultants to the Kouga
Council was considered by
ASR. However, the point was
made that at least five
groynes would have been
needed with a length of 300
meters each. This
however, would only have
resulted in some sand
deposition offshore at the
head of the groynes but not
on the beach.
-
New Findings: The
data collected and analysed
by ASR shows conclusively
that the previous view that
sand was transported from
South to North along the
beach is incorrect. Due to
wave refraction around Seal
Point / Cape St Francis the
direction of the waves
varies quite significantly
along the length of the
beach. This in conjunction
with the lack of natural
sand replenishment is
resulting in the sand being
lost offshore rather than
moving along the beach.
-
Submerged Reefs:
The findings from the Draft
ASR Report clearly indicates
that the submerged reef
option is both feasible and
affordable. Based on
the initial findings it is
estimated that the submerged
reefs are the correct way
forward. This is confirmed
by the work also being
undertaken by ASR for the
Nelson Mandela Metro who are
looking at two beaches
(Pollock and Wells Estate)
with the possibility of a
further two in the future.
Integrated Approach: A
fully integrated approach is
being employed in the
project which includes the
beach and dune system, the
Kromme River Estuary as well
as the canal system. This
will allow for more
effective management of the
environment from an overall
perspective.
-
Further Data Collection:
As a result of the findings
in the Draft ASR Report a
certain amount of additional
data collection is planned
prior to the design phase.
This will be completed
during June/July, 2006 prior
to Dylan Anderson leaving to
assist in the modelling,
design and final report with
the ASR team in New Zealand.
This part of the project
will extend through to the
end of November, 2006.
Department
of the Environment and Tourism
Alan Tonkin
from the SFB Beach Trust who
chaired the meeting also took
time to mention the support
received from the National
Minister of Environmental
Affairs and Tourism. Following
the meeting between the SFB
Beach Trust and the Minister in
Pretoria on 19 April, 2006. Mr
van Schalkwyk is very supportive
of the activities of the Beach
Trust and undertook to visit St
Francis as soon as possible.
In addition,
it was mentioned that Dr Niel
Malan, the Deputy Director of
the Integrated Coastal
Management Unit from the
Department of the Environment
and Tourism was at the meeting.
This was in addition to visiting
St Francis to meet with the
Beach Trust the previous week.
Dr Malan had also indicated that
the Minister is planning to
visit St Francis Bay in August,
2006. This is still to be
confirmed.
Dr Malan made
the point to the Beach Trust
that the fully integrated
approach by the Beach Trust is
supported by his unit. In
addition, as this is the first
project of its type in Africa,
the Department of Marine and
Coastal Management are also
taking a keen interest in this
project.
Shaw Mead and
Dylan Anderson plus Emlyn Horne
and Alan Tonkin from the SFB
Beach Trust also held a meeting
with Nicholas Scarr from the
Provincial Department of
Environmental Affairs and
Tourism on Monday 22 May, 2006
in Port Elizabeth. This was
prior to Shaw Mead leaving the
country to return home. This was
to ensure that all interested
parties are fully aware of
current progress with the Beach
Project.
Summary
and Conclusion
The Beach
Project is well on the way to
producing real results by the
end of 2006. At that stage the
Beach Trust will be in a
position to provide detailed
information on final design and
costs as well as financing
options.
It is
important to emphasise that St
Francis without a beach will be
severely disadvantaged compared
to other similar holiday
destinations. This could result
in the real possibility of
people moving away from SFB and
the contraction of the local
economy with related job
losses. This in turn could
result in property prices being
affected which will create a
major issue not only for St
Francis but also for Kouga.
In
concluding, the SFB Beach Trust
wish to point out that we still
require some R400k in order to
complete the final design and
costing. The support of SFB
residents is required, however
large or small,in order to
complete this very necessary
project for the future of St
Francis. For further
information contact us at
www.stfrancisbay.org
Alan Tonkin
Chairman:
SFB Beach Trust
May, 2006
|